March 2023

March 2023

March 5, 2023 – A curb has been installed around the gatehouse and filled in with crushed stones.  Digging has also begun on the front corner of the main property, which included the installation of drain boxes along the top of the main property.

March 12, 2023 – Expansion of the water retention basin has begun, piping has been attached in the ground on the west side of Alexandria Hall, and topsoil has begun to be stripped where the chapel will be located.

March 19, 2023 – Progress has been made with the water pipes, as well as the water basin.

 