February 5, 2023 – The fence has been completed and a footpath is being built alongside the entrance.
![P1022592](https://www.scs.edu/wp-content/uploads/2023/06/P1022592-768x576.jpg)
![P1022594](https://www.scs.edu/wp-content/uploads/2023/06/P1022594-768x576.jpg)
![P1022599](https://www.scs.edu/wp-content/uploads/2023/06/P1022599-768x576.jpg)
![P1022600](https://www.scs.edu/wp-content/uploads/2023/06/P1022600-768x576.jpg)
![P1022613](https://www.scs.edu/wp-content/uploads/2023/06/P1022613-768x576.jpg)
Previous
Next
February 18, 2023 – The front drainage pipe has been completed and progress has been made with the sewer pipe junctions.
![P1022627](https://www.scs.edu/wp-content/uploads/2023/02/P1022627-768x576.jpg)
![P1022614](https://www.scs.edu/wp-content/uploads/2023/02/P1022614-768x576.jpg)
![P1022632](https://www.scs.edu/wp-content/uploads/2023/02/P1022632-768x576.jpg)
![P1022640](https://www.scs.edu/wp-content/uploads/2023/02/P1022640-768x576.jpg)
![P1022635](https://www.scs.edu/wp-content/uploads/2023/02/P1022635-768x576.jpg)
Previous
Next
February 26, 2023 – A new junction box was placed at the base of the water retention basin, two drills are now on the lawn where the chapel will be located, and a water trap was built in the front of the main construction area.