October 22, 2023 – Exterior wall and roof frames are still in progress.
October 15, 2023 – The exterior wall frame and roof frame for the college dormitory have been completed and the exterior wall frame for the student life center has been partially completed.
October 1, 2023 – The outside walls of the first floor of the student life center and the first and second floors of the college building are in progress and three transformer boxes have been installed.