News & Events | Relocation Effort | Photo Archive | April 2023
April 2023





April 16, 2023 – The water mains for the fire system have been completed, the dirt on the land where the Chapel will be built has been terraced, and a vision-impaired sidewalk end has been installed on the end of the pedestrian walkway.






April 23, 2023 – The Evans Road entrance to the campus has been reopened, a building outline has been set, the access road behind Alexandria Hall is in the process of being built, and a dirt mound has been placed on the side of Alexandria Hall.